24/06708/FU decided withdrawn
Last updated 20/07/2025, 10:09
Application to install EV charging units and related electrical equipment, including a feeder pillar and substation, on an existing car park to create an EV charging facility.
Full Planning Application
Rawdon
Full Proposal
Siting of EV charging units together with associated ancillary electrical equipment including feeder pillar and substation on existing car park, to create EV charging facility
Application Timeline
- Application Registered
- N/A
- Application Validated
- 21/11/2024
- Target Decision Date
- 16/01/2025
- Committee Date
- N/A
- Decision Made
- 15/01/2025
- Decision Issued
- 15/01/2025
Applicant
Mr R Heap