24/05982/FU decided approve
Last updated 20/07/2025, 10:49
Application to demolish the existing substation and build a new one with related infrastructure works, landscaping, and changes to parking.
Full Planning Application
Leeds, LS2 3AR
LS2 3ARFull Proposal
Demolition of existing substation; erection of new substation with associated infrastructure works; hard and soft landscaping and amended parking provision
Application Timeline
- Application Registered
- N/A
- Application Validated
- 15/10/2024
- Target Decision Date
- 10/12/2024
- Committee Date
- N/A
- Decision Made
- 07/02/2025
- Decision Issued
- 07/02/2025
Applicant
University Of Leeds