25/04967/FU decided approve
Last updated 11/11/2025, 18:09
Application to build an electric vehicle charging hub with a substation, charging bays, and associated works.
Full Planning Application
Capitol Boulevard, Tingley, Leeds, LS27 0TS
LS27 0TSFull Proposal
Electric vehicle charging hub with substation, charging bays and associated works
Application Timeline
- Application Registered
- N/A
- Application Validated
- 02/09/2025
- Target Decision Date
- 28/10/2025
- Committee Date
- N/A
- Decision Made
- 11/11/2025
- Decision Issued
- 11/11/2025
Applicant
IONITY GmbH