24/07419/FU decided approve
Last updated 20/07/2025, 11:19
Application to install 22 electric vehicle charging bays in the existing car park, along with a new substation and related infrastructure.
Full Planning Application
171, Elland Road, Leeds, LS11 8BU
LS11 8BUFull Proposal
22 EV car charging bays to existing car park, including a new substation and associated infrastructure
Application Timeline
- Application Registered
- N/A
- Application Validated
- 24/12/2024
- Target Decision Date
- 25/03/2025
- Committee Date
- N/A
- Decision Made
- 03/04/2025
- Decision Issued
- 03/04/2025
Applicant
E.ON Drive Infrastructure UK