25/06814/FU decided approve
Last updated 20/01/2026, 18:08
Installation of 14 electric vehicle charging stations, a substation, and a feeder pillar, including underground cabling to an existing connection point.
Full Planning Application
Cardigan Fields, Kirkstall Road, Leeds, LS4 2DG
LS4 2DGFull Proposal
Installation of 14no. electric vehicle charging stations, substation and feeder pillar including installation of associated underground cabling to an existing underground point of connection
Application Timeline
- Application Registered
- N/A
- Application Validated
- 26/11/2025
- Target Decision Date
- 21/01/2026
- Committee Date
- N/A
- Decision Made
- 20/01/2026
- Decision Issued
- 20/01/2026
Applicant
Raw Charging